Measuring data centre energy for Green Mark
Set the facility and IT measurement boundaries, calculate PUE over a common period and prepare evidence for a Green Mark review.
Start with the project score sheet
BCA and IMDA publish Green Mark criteria for new and existing data centres. BCA provides separate score sheets for those projects and an in-operation route for recertification. Select the applicable documents with the assessment team before finalising the metering design.
Power usage effectiveness (PUE) is one part of the assessment. The criteria also address cooling, air management, the IT power chain and other aspects of performance. A project target for PUE needs a defined measurement boundary, operating conditions and an agreed reporting period.
Trace both sides of the ratio
PUE is total data centre energy divided by IT equipment energy over the same period. If a facility uses 1,500 MWh and its IT equipment uses 1,000 MWh during that period, PUE is 1.50. Record both energy totals with the ratio so reviewers can see what changed.
- Mark incoming supplies, shared plant and any on-site energy sources on the facility diagram.
- Identify the IT measurement points on both sides of a dual supply. Trace transfers between feeds to avoid counting the same load twice.
- Document where cooling plant, UPS losses and other supporting loads enter the facility total. Record how shared services are allocated.
Read the trends behind the number
Compare IT energy with the remaining facility energy. A lightly loaded hall can show higher PUE even if its absolute energy use falls. Read the trend alongside occupancy, IT load, cooling operating hours and maintenance events. Branch meters can help locate a change by hall or PDU.
Prepare the evidence for review
Keep dated diagrams, meter identifiers, ratios and interval exports together. Record the treatment of missing intervals, equipment replacements and changes to the boundary. Agree access and commissioning windows with the site operations team when a measurement point changes.
For a new hall, distinguish design assumptions from operating measurements. For an existing hall, provide comparable periods and explain significant changes in load. Confirm the evidence and rating prerequisites against the applicable BCA score sheet.